Applications for payment and retentions
For example: A £120,000 heating installation with 5% retention. By the end of March, £30,000 of work is done: £1,500 is held back, so application 1 is £28,500. By the end of April it’s £54,000: less £2,700 retention and the £28,500 already applied for, application 2 is £22,800.
Les questions qu’on nous pose
What goes in “work done to date”?
The value of all the contract work done since the start, not just this month. Extra work the customer asked for goes in “variations to date”. You can type a percentage of the contract to work it out.
When does the retention come back?
Half at practical completion (when the job is finished and handed over), and the rest at the end of the defects period, usually 12 months later. Both are applied for like any other application.
The customer paid less than I applied for
Change the invoice to what they certified. Next month, apply for the full value of the work done to date again: anything not paid is still in it.
Cet article vous a-t-il aidé ?
Merci de nous l’avoir dit.
Désolés que cela n’ait pas répondu à votre question. Merci de nous l’avoir signalé : cela nous aide à améliorer les guides.
Besoin d’aide supplémentaire ? Connectez-vous à votre compte et ouvrez un ticket d’assistance. Les personnes qui ont écrit le code vous aideront, et la plupart des tickets reçoivent une réponse le jour ouvré même.