Applications for payment and retentions

For contract work paid in stages. Put in the contract’s value and the retention the customer holds back. Each month, put in the value of the work done so far: the retention and what you’ve already applied for are taken off, and what’s left is this application. Send it to the customer, then make it an invoice. Half the retention comes back at practical completion and the rest when the defects period ends, and you’re reminded when it’s due.

For example: A £120,000 heating installation with 5% retention. By the end of March, £30,000 of work is done: £1,500 is held back, so application 1 is £28,500. By the end of April it’s £54,000: less £2,700 retention and the £28,500 already applied for, application 2 is £22,800.

Lo que nos suelen preguntar

What goes in “work done to date”?
The value of all the contract work done since the start, not just this month. Extra work the customer asked for goes in “variations to date”. You can type a percentage of the contract to work it out.

When does the retention come back?
Half at practical completion (when the job is finished and handed over), and the rest at the end of the defects period, usually 12 months later. Both are applied for like any other application.

The customer paid less than I applied for
Change the invoice to what they certified. Next month, apply for the full value of the work done to date again: anything not paid is still in it.