Applications for payment and retentions
For example: A £120,000 heating installation with 5% retention. By the end of March, £30,000 of work is done: £1,500 is held back, so application 1 is £28,500. By the end of April it’s £54,000: less £2,700 retention and the £28,500 already applied for, application 2 is £22,800.
Frågor folk ställer
What goes in “work done to date”?
The value of all the contract work done since the start, not just this month. Extra work the customer asked for goes in “variations to date”. You can type a percentage of the contract to work it out.
When does the retention come back?
Half at practical completion (when the job is finished and handed over), and the rest at the end of the defects period, usually 12 months later. Both are applied for like any other application.
The customer paid less than I applied for
Change the invoice to what they certified. Next month, apply for the full value of the work done to date again: anything not paid is still in it.
Var detta till hjälp?
Tack för att du berättade.
Tråkigt att detta inte gav svar. Tack för att du sa till: vi använder det för att förbättra guiderna.
Behöver du fortfarande hjälp? Logga in på ditt konto och skapa ett supportärende. De som skrev koden hjälper dig, och de flesta ärenden besvaras samma arbetsdag.